Lilleker-Bros-Lynemouth-Case-Study-

Client;

Sir Robert McAlpine Ltd
Lynemouth Biomass Plant

 

Project;

  • Provision of electrical installation works to Lynemouth Power Station, Ashington as it converted from Coal to Biomass
  • Project involved the road and rail delivery buildings, main storage silos and the large conveyor systems designed to handle and deliver the fuel as part of the impressive biomass delivery system.
  • The Power Station will make a significant contribution to the National Grid and increase the UK’s current power generation capacity by providing an addition of 390 megawatts of Low Carbon Electricity.

 

Scope;

  • Listec Temperature Measuring System
  • Fireworks Water Mist System
  • GreCon Trace Heating System
  • Land IR Detection Equipment
  • Listec Temperature Measuring System
  • UPS System
  • Rail offloading
  • Silo Discharge to all 6 Silos
  • Silo Foam Installation
  • Magnets
  • Solenoid Valves
  • Pull Keys
  • Lighting and small power

 

Value

£900,000K

Client

Cemex UK Ltd
South Ferriby

Project

  • Quarry Dewatering Pumps

Scope

  • Containerised 11kv Substation
  • MV and LV Power, Control
  • Instrumentation Cabling
  • Containment within the Quarry

Value

  • £135,000.00

Client

Solway Foods, 2 Sisters Food Group, Worksop
Worksop

Project

  • Refurbishment of Factory 4 & 5 Sandwich halls and associated despatch, tray wash and prep areas.
  • Disconnection and strip out of existing installation.
  • Installation of 9 No. sandwich manufacturing lines and associated power and control.
  • Replacing existing fluorescent lighting to both factories with new LED energy saving fittings.
  • Installation of IP67 three phase and single phase GRP RCD socket outlets to perimeter of factories.
  • Upgrade existing fire alarms and emergency lighting to both factories.
  • Upgrading of distribution and containment matrix to accommodate the above.
  • Testing and commissioning of the above.
  • Refurbishment of offices to the above factory.
  • Installation of new CCTV throughout the factories and associated offices, plantroom and amenities.
  • Replace existing SON lighting with new LED energy saving external flood lighting to perimeter and car parks.

Scope

  • Line distribution boards and sub mains.
  • Power supplies to plant.
  • Small power to general sockets, inescticutors and equipment.
  • Factory Lighting and Emergency Lighting.
  • Fire Alarm upgrades.
  • CCTV installation.
  • Office lighting and emergency lighting.
  • Office small power and data containment.
  • External lighting.

Value

  • £380,000.00

Client

BWSC, Denmark
Nottingham

Project

  • Brigg Renewable Energy Project, 42 MW straw burning power station

Scope

  • Full Electrical Installation including;
  • Power/Control/Instrument Containment
  • Power/Control Instrument Cabling
  • Lighting/Small Power/Fire Alarm

Value

  • £1.3 Million

Client

G F Tomlinson
Derby

Project

  • Meter Provider, Markham Vale Jct 29A
  • Full M&E Services to new office and warehouse facility Design & Building Project
  • First BIM model project

Scope

  • Lighting
  • Power
  • Security
  • Heating
  • Ventilation
  • Air Conditioning
  • Gas Heating to Warehouse

Value

  • £300,000.00

Client

Kier Services

Project

  • Grantham Hospital Maternity Block Level 2 M&E Package
  • Lincoln Hospital Maternity Block Level 5 Mechanical Package

Scope

  • Grantham – Replace heating system and lighting including
  • Radiant Panels
  • Radiators
  • Lighting Control
  • Ventilation Modifications
  • Lincoln – Full Refurbishment of Mechanical Services
  • Heating Modifications
  • Ventilation Modifications
  • New Water Services
  • New AC Services
  • BMS Controls
  • Sanitary Ware

Value

  • £835,000.00

Client

Tata Steel
Stockbridge

Project

  • Various Dayworks Projects 2012 – 2015

Scope

  • Supply and installation of SWA Cabling.
  • Replacement of distribution boards and motor control centres.
  • Supply and installation of cable ladder rack and tray.
  • Supply and installation of metal trunking and conduit.
  • Installation Plant Immobilisation schemes.
  • Supply and installation of mineral insulated cables.
  • Full fire alarm and emergency lighting installations.
  • Rewiring motor roller beds and manipulators.
  • Replacement of lighting with LED.
  • Full design and rewired of the engineering offices.
  • Supply and installation of new isolation equipment to old switchgear.
  • Street and rail side lighting.
  • Furnace supplies and cooling beds.
  • Manufacture of Control panels.
  • Complete testing to BS 7671:2008 + A32015.
  • A full design, installation and commissioning service.

Value

  • £100,000.00

Call us: 01709 374073

Get in touch with us today
to find out how we can help you and your company!

Not a fan of the phone?

We understand it’s not always convenient to make a call, so why not send us an email and we will get back to you ASAP.